Project:
2165 Rialma Companhia Energética III S/A. – Santa Edwiges III Small Hydro Power Plant – Small Scale CDM Project
- Issuance Request
Project | 2165: Rialma Companhia Energética III S/A. – Santa Edwiges III Small Hydro Power Plant – Small Scale CDM Project |
---|---|
ISSUANCE STATUS | Issued (on 02 Jan 13) completeness check: complete | info & rep check: concluded |
Monitoring period | 07 Aug 09 - 31 Mar 12 |
Monitoring report |
![]() |
Request for issuance |
![]() |
Amount of CERs |
CERs issued up to 31 December 2012:
45,341
Serial Range:
Block start: BR-5-78332474-1-1-0-2165
Block end: BR-5-78377814-1-1-0-2165
|
Verification and certification reports |
VVS/VVM version:
VVM 1.2
![]() ![]() |
Additional documents |
![]() ![]() |
Previous submissions
Submission date | Outcome |
---|---|
21 Aug 12 | CC incomplete |
Offset now: visit the United Nations Carbon Offset Platform