Registration Request for Review Form
CDM project activity/programme of activities registration request review form (CDM-REGR-FORM) (Version 03.0) |
---|
Reference number of the proposed CDM project activity/programme of activities (PoA) submitted for registration | 2147 |
---|---|
Title of the proposed CDM project activity/PoA submitted for registration | Sichuan Tongjiang Gaokeng Hydropower Station Project |
Please indicate, in accordance with paragraphs 37 and 40 of the CDM modalities and procedures, which validation requirement(s) may require review. A list of requirements is provided below. Please provide reasons in support of the request for review. Including any supporting documentation. | |
The following are requirements derived from paragraph 37 of the CDM modalities and procedures: | |
![]() ![]() ![]() ![]() ![]() ![]() ![]() |
|
The following are requirements derived from paragraph 40 of the CDM modalities and procedures: | |
![]() ![]() ![]() ![]() ![]() ![]() |
|
![]() |
|
Additional information | |
1. The DOE is requested to provide further substantiation of the suitability of the benchmark given that it was published in 1995 and the investment was made in 2005. Further, noting that the local authorities approved the PDR on the basis of an equity IRR, the DOE is requested to verify that the benchmark is a suitable comparator for an project IRR calculation. 2. The PDD states that the expected annual power generation is 59.84 million kWh. However the net export to the grid is expected to be 50.56 million kWh. This loss of in excess of 15% of power generation should be further explained. 3. The PDD published for global stakeholder consultation applied a grid emission factor of 0.89961 tCO2/MWh. The PDD submitted for registration applies a factor of 0.97455 tCO2/MWh. The validation report does not explain the reasons why a change to the factor was requested. The DOE is requested to provide justification. |
|
Date | 24 Dec 08 |