14:28 01 Jul 25
Registration Request for Review Form
CDM project activity/programme of activities registration request review form (CDM-REGR-FORM) (Version 03.0) |
---|
Reference number of the proposed CDM project activity/programme of activities (PoA) submitted for registration | 2108 |
---|---|
Title of the proposed CDM project activity/PoA submitted for registration | Gansu Datonghe Tiecheng Hydropower Station Project |
Please indicate, in accordance with paragraphs 37 and 40 of the CDM modalities and procedures, which validation requirement(s) may require review. A list of requirements is provided below. Please provide reasons in support of the request for review. Including any supporting documentation. | |
The following are requirements derived from paragraph 37 of the CDM modalities and procedures: | |
![]() ![]() ![]() ![]() ![]() ![]() ![]() |
|
The following are requirements derived from paragraph 40 of the CDM modalities and procedures: | |
![]() ![]() ![]() ![]() ![]() ![]() |
|
![]() |
|
Additional information | |
1. The PP/DOE are requested to clarify: a) the difference between the O&M costs, bank loan financing and interest and IRR results stated in the PDD and Validation Report and the ones used in the spreadsheet provided and; b) the appropriateness of the period of analysis applied in the investment analysis compared to the operational lifetime of the project. 2. The DOE is requested to clarify the opinion that the emission factor (0.861 tCO2/MWh) is more conservative than that published by NDRC in December 2006 (0.841 tCO2/MWh). |
|
Date | 20 Jan 09 |