01:50 12 Sep 25
Registration Request for Review Form
CDM project activity/programme of activities registration request review form (CDM-REGR-FORM) (Version 03.0) |
---|
Reference number of the proposed CDM project activity/programme of activities (PoA) submitted for registration | 2104 |
---|---|
Title of the proposed CDM project activity/PoA submitted for registration | Baishuiquan Hydropower Project, Guizhou Province, China |
Please indicate, in accordance with paragraphs 37 and 40 of the CDM modalities and procedures, which validation requirement(s) may require review. A list of requirements is provided below. Please provide reasons in support of the request for review. Including any supporting documentation. | |
The following are requirements derived from paragraph 37 of the CDM modalities and procedures: | |
![]() ![]() ![]() ![]() ![]() ![]() ![]() |
|
The following are requirements derived from paragraph 40 of the CDM modalities and procedures: | |
![]() ![]() ![]() ![]() ![]() ![]() |
|
![]() |
|
Additional information | |
1. The DOE is requested to justify the suitability of the 10% benchmark, in particular as it was issued in 1995, for assessing an investment decision made in 2004. 2. The DOE is requested to confirm the common practice analysis, in particular the essential distinctions between the project activity and similar projects as cited in the PDD. 3. The DOE is requested to confirm that the ex-ante emission factor of 0.84335 tCO2/MWh complies with the requirement of the methodology regarding the use of the most up-to-date data at the time of validation as the PDD for GSC used a different emission factor (0.7784 tCO2/MWh). |
|
Date | 21 Dec 08 |