18:05 01 Jul 25
Project:
2088 Hebei Yuxian Kongzhongcaoyuan 49.5MW Wind Farm Project
- Issuance Request
Project | 2088: Hebei Yuxian Kongzhongcaoyuan 49.5MW Wind Farm Project |
---|---|
ISSUANCE STATUS | Issued (on 07 Jun 22) completeness check: complete | info & rep check: concluded |
Monitoring period | 01 Jan 13 - 22 Feb 16 |
Monitoring report |
![]() |
Request for issuance |
![]() |
Amount of CERs |
CERs issued from 01 Jan 2013 until 31 December 2020:
397,178
Serial Range:
Block start: CN-5-1139974799-2-2-0-2088
Block end: CN-5-1140371976-2-2-0-2088
|
Verification and certification reports |
VVS/VVM version:
VVS-PA 3.0
![]() ![]() |
Additional documents |
![]() ![]() |
Offset now: visit the United Nations Carbon Offset Platform
Connect with us: