Project: 2055 Shangri-La Langdu River 3rd Level Hydropower Station - Issuance Request
Project 2055: Shangri-La Langdu River 3rd Level Hydropower Station
 
ISSUANCE STATUS Issued (on 11 Jan 13)   completeness check: complete | info & rep check: concluded
Monitoring period 26 Jun 11 - 15 Aug 12
Monitoring report Monitoring report (176 KB)
 
Request for issuance Signed form (640 KB)
Amount of CERs CERs issued up to 31 December 2012: 22,121
Serial Range: Block start: CN-5-714651046-1-1-0-2055     Block end: CN-5-714673166-1-1-0-2055
Verification and certification reports VVS/VVM version: VVS 2.0
Certification report (1306 KB)
Verification report (1306 KB)
Additional documents 2055 2 Monitoring Report (178 KB)
2055 2 CER Calculation (31 KB)