Project: 1987 Sichuan Pingwu Xiannvbao Hydropower Station - Issuance Request
Project 1987: Sichuan Pingwu Xiannvbao Hydropower Station
 
ISSUANCE STATUS Issued (on 01 Mar 23)   completeness check | info & rep check: concluded
Monitoring period 21 Jul 12 - 20 Dec 12
Monitoring report Monitoring report (565 KB)
 
Request for issuance Signed form (176 KB)
Amount of CERs CERs issued up to 31 December 2012: 115,182
Serial Range: Block start: CN-5-1178222233-1-1-0-1987     Block end: CN-5-1178337414-1-1-0-1987
Verification and certification reports VVS/VVM version: VVS-PA 3.0
Certification report (659 KB)
Verification report (659 KB)
Additional documents Untitled (uploaded 19 Dec 22 08:11:17) (563 KB)
Untitled (uploaded 19 Dec 22 08:12:26) (38 KB)

Previous submissions

Submission date Outcome
13 Sep 22 CC complete | I&R incomplete