Project: 1984 Sichuan Wanyuan Baiyangxi Hydropower Station - Issuance Request
Project 1984: Sichuan Wanyuan Baiyangxi Hydropower Station
 
ISSUANCE STATUS Issued (on 17 Dec 12)   completeness check: complete | info & rep check: concluded
Monitoring period 26 Jan 12 - 25 Aug 12
Monitoring report Monitoring report (102 KB)
 
Request for issuance Signed form (85 KB)
Amount of CERs CERs issued up to 31 December 2012: 66,275
Serial Range: Block start: CN-5-686171984-1-1-0-1984     Block end: CN-5-686238258-1-1-0-1984
Verification and certification reports VVS/VVM version: VVS 2.0
Certification report (239 KB)
Verification report (239 KB)
Additional documents 1984-20121001-MR (102 KB)