08:34 21 Jan 25
Project:
1743 Yunnan Yuanjiang Lutong Hydropower Station
- Crediting Period Renewal Request
[]
Project |
1743: Yunnan Yuanjiang Lutong Hydropower Station
- project design document (1475 KB) PDD appendices Appendix 1 - ER calculation spreadsheet-Lutong (63 KB) - crediting period renewal form (1217 KB) |
---|---|
Methodologies Used |
AMS-I.D. ver. 18 -
Grid connected renewable electricity generation
|
VVS Version | VVS 7.0 |
Standardized baselines used | N/A |
Amount of Reductions | 29,481 metric tonnes CO2 equivalent per annum |
Validation Opinion | Validation opinion (1761 KB) |
Renewal Date |
21 Oct 15
(Renewable - Expired)
(view history)
completeness check: complete
info & rep check: concluded
Renewal no longer possible
|
Crediting Period (requested for renewal) |
07 Aug 15 - 06 Aug 22
Other crediting period(s): 07 Aug 08 - 06 Aug 15 |
Requests for Issuance
and related documentation |
Monitoring report: 07 Aug 2015 - 31 Dec 2020 (750 KB) Issuance request state: Issued CERs requested from 01 Jan 2013 until 31 December 2020: 99755 Serial Range: Block start: CN-5-1153921368-2-2-0-1743 Block end: CN-5-1154021122-2-2-0-1743 [Full view and history] |