Registration Request for Review Form
CDM project activity/programme of activities registration request review form (CDM-REGR-FORM) (Version 03.0) |
---|
Reference number of the proposed CDM project activity/programme of activities (PoA) submitted for registration | 1658 |
---|---|
Title of the proposed CDM project activity/PoA submitted for registration | Yinshan Profiled Iron Co., Ltd. 25 MW Waste Gas Power Generation Project of Laiwu Iron & Steel Group Corp. |
Please indicate, in accordance with paragraphs 37 and 40 of the CDM modalities and procedures, which validation requirement(s) may require review. A list of requirements is provided below. Please provide reasons in support of the request for review. Including any supporting documentation. | |
The following are requirements derived from paragraph 37 of the CDM modalities and procedures: | |
![]() ![]() ![]() ![]() ![]() ![]() ![]() |
|
The following are requirements derived from paragraph 40 of the CDM modalities and procedures: | |
![]() ![]() ![]() ![]() ![]() ![]() |
|
![]() |
|
Additional information | |
1. Further clarification is required on (a) how the DOE has validated the investment barriers and (b) the common practice analysis, in particular the identification of the similar project activity. 2. Further clarification is required on how the DOE has validated the suitability of the input values, as per the guidance of EB 38 paragraph 54 (c). 3. If the barriers to the project activity cannot be further substantiated, an economic comparison of the proposed baseline and the project activity without the CDM must be conducted to determine the baseline scenario. 4. Further clarification is required on why the combined margin emission factor in the PDD for request for registration is not consistent with the PDD published for global stakeholder process. 5. Further clarification is required on how the DOE has validated the electricity consumption in pre project scenario from both grid and captive power plant and current status of the waste gas based captive power plant, which produce 4.25% of the total electricity requirement in the pre-project. |
|
Date | 21 Aug 08 |