04:09 30 Jan 25
Issuance Request for Review Form
CDM project activity/programme of activities issuance request review form (CDM-ISSR-FORM) (Version 03.0) |
---|
Project title of the project activity or programme of activities (PoA) for which issuance is requested | Anshan Iron and Steel Group Corporation (Anshan) Blast Furnace Gas Combined Cycle Power Plant Project (1609) |
---|---|
DOE that requested for issuance and date of request | DNV (13 May 11) |
Please indicate, in accordance with paragraphs 65 of the CDM modalities and procedures, for which reason(s) you request review | |
Incompetence | |
Please indicate reasons for the request for review | |
The DOE verified (Verification Report, Page 8) that the monitoring plan contained in the registered PDD complies with the applicable methodology as required by the VVM paragraph 199 (EB 55 report, annex 1). However, the approved monitoring plan does not require the measurement of the volume of the auxiliary fuel used by project activity (Qi) which is required by the applicable methodology ACM0004 version 2. Clarification is required on how the DOE concluded that the monitoring plan was in accordance with the applicable methodology. | |
Date | 25 Jun 11 |