Project:
1609 Anshan Iron and Steel Group Corporation (Anshan) Blast Furnace Gas Combined Cycle Power Plant Project
- Issuance Request
Project | 1609: Anshan Iron and Steel Group Corporation (Anshan) Blast Furnace Gas Combined Cycle Power Plant Project |
---|---|
ISSUANCE STATUS | Issued (on 06 Oct 10) |
Monitoring period | 01 Sep 09 - 28 Feb 10 |
Monitoring report | Monitoring report (357 KB) |
Request for issuance | Signed form (557 KB) |
Amount of CERs |
CERs issued up to 31 December 2012:
654,793
Serial Range:
Block start: CN-5-223474591-1-1-0-1609
Block end: CN-5-224129383-1-1-0-1609
|
Verification and certification reports |
Certification report (175 KB)
Verification report (175 KB) |
Additional documents |
CER Sheet 1609 (89 KB)
MR 1609 (364 KB) |