Project: 1609 Anshan Iron and Steel Group Corporation (Anshan) Blast Furnace Gas Combined Cycle Power Plant Project - Issuance Request
Project 1609: Anshan Iron and Steel Group Corporation (Anshan) Blast Furnace Gas Combined Cycle Power Plant Project
 
ISSUANCE STATUS Issued (on 25 Jan 10)  
Monitoring period 03 Dec 08 - 31 Mar 09
Monitoring report Monitoring report (422 KB)
 
Request for issuance Signed form (678 KB)
Amount of CERs CERs issued up to 31 December 2012: 496,778
Serial Range: Block start: CN-5-175870317-1-1-0-1609     Block end: CN-5-176367094-1-1-0-1609
Verification and certification reports Certification report (182 KB)
Verification report (182 KB)
Additional documents CER Sheet 1609 (89 KB)
MR 1609 (398 KB)