Project:
1482 Conversion of existing open cycle gas turbine to combined cycle at the Central Termica Patagonia power station, Comodoro Rivadavia, Argentina
- Issuance Request
Project | 1482: Conversion of existing open cycle gas turbine to combined cycle at the Central Termica Patagonia power station, Comodoro Rivadavia, Argentina |
---|---|
ISSUANCE STATUS | Issued (on 15 Jul 13) completeness check: complete | info & rep check: concluded |
Monitoring period | 01 Jun 12 - 31 Dec 12 |
Monitoring report |
![]() |
Request for issuance |
![]() |
Amount of CERs |
CERs issued up to 31 December 2012:
47,544
Serial Range:
Block start: AR-5-14216431-1-1-0-1482
Block end: AR-5-14263974-1-1-0-1482
|
Verification and certification reports |
VVS/VVM version:
VVS 3.0
![]() ![]() |