02:05 11 Feb 25
Project:
1482 Conversion of existing open cycle gas turbine to combined cycle at the Central Termica Patagonia power station, Comodoro Rivadavia, Argentina
- Issuance Request
Project | 1482: Conversion of existing open cycle gas turbine to combined cycle at the Central Termica Patagonia power station, Comodoro Rivadavia, Argentina |
---|---|
ISSUANCE STATUS | Issued (on 21 Jun 13) completeness check: complete | info & rep check: concluded |
Monitoring period | 01 Jun 11 - 31 May 12 |
Monitoring report |
![]() |
Request for issuance |
![]() |
Amount of CERs |
CERs issued up to 31 December 2012:
76,063
Serial Range:
Block start: AR-5-14140368-1-1-0-1482
Block end: AR-5-14216430-1-1-0-1482
|
Verification and certification reports |
VVS/VVM version:
VVS 3.0
![]() ![]() |
Additional documents |
![]() ![]() ![]() ![]() ![]() |
Previous submissions
Submission date | Outcome |
---|
Offset now: visit the United Nations Carbon Offset Platform
Connect with us: