Project: 1416 Baotou Iron & Steel Blast Furnace Gas Combined Cycle Power Plant Project - Issuance Request
Project 1416: Baotou Iron & Steel Blast Furnace Gas Combined Cycle Power Plant Project
 
ISSUANCE STATUS Issued (on 25 Oct 11)   completeness check: complete | info & rep check: concluded
Monitoring period 27 Nov 10 - 27 May 11
Monitoring report Monitoring report (278 KB)
 
Request for issuance Signed form (288 KB)
Amount of CERs CERs issued up to 31 December 2012: 703,079
Serial Range: Block start: CN-5-438958167-1-1-0-1416     Block end: CN-5-439661245-1-1-0-1416
Verification and certification reports Certification report (579 KB)
Verification report (579 KB)
Additional documents Baogang CCPP ER Monitoring Report Period 6-V3 20110719 (278 KB)
Baogang_ER Spreadsheet_MP6_V3_20110719 (392 KB)