Issuance Request for Review Form


CDM project activity/programme of activities
issuance request review form (CDM-ISSR-FORM)
(Version 03.0)

Project title of the project activity or programme of activities (PoA) for which issuance is requestedInner Mongolia Zhuozi 40MW Wind Power Project (1327)
DOE that requested for issuance and date of requestBVI (23 Aug 09)
Please indicate, in accordance with paragraphs 65 of the CDM modalities and procedures, for which reason(s) you request review
Incompetence
Please indicate reasons for the request for review
1. The DOE is requested to clarify how it verified the appropriateness of the calibration frequency considering that the period between the first calibration (05/04/2007) and the second calibration (26/11/2008) is longer than a year while the monitoring plan describes that the metering equipment are calibrated and checked annually.

2. The DOE is requested to clarify how it verified that the meters used for the monitoring of the electricity imported through the 10 kV back up line and their maintenance are in line with the monitoring plan.
Date 03 Nov 09