20:37 14 May 25
Project:
1171 Project for the catalytic reduction of N2O emissions with a secondary catalyst inside the ammonia reactor of the No. 9 nitric acid plant at African Explosives Ltd (“AEL”), South Africa
- Issuance Request
Project | 1171: Project for the catalytic reduction of N2O emissions with a secondary catalyst inside the ammonia reactor of the No. 9 nitric acid plant at African Explosives Ltd (“AEL”), South Africa |
---|---|
ISSUANCE STATUS | Issued (on 23 Oct 14) completeness check: complete | info & rep check: concluded |
Monitoring period | 12 Mar 12 - 13 Mar 13 |
Monitoring report |
![]() |
Requests for post-registration changes submitted with the issuance request | PRC-1171-001 |
Request for issuance |
![]() |
Amount of CERs |
CERs issued up to 31 December 2012:
48,571
CERs issued from 01 Jan 2013 until 31 December 2020: 15,251 Total amount of CERs: 63,822
Serial Range:
Block start: ZA-5-8586929-1-1-0-1171
Block end: ZA-5-8635499-1-1-0-1171
Serial Range: Block start: ZA-5-8635500-2-2-0-1171 Block end: ZA-5-8650750-2-2-0-1171 |
Verification and certification reports |
VVS/VVM version:
VVS 5.0
![]() ![]() |
Additional documents |
![]() |
Offset now: visit the United Nations Carbon Offset Platform