Issuance Request for Review Form


CDM project activity/programme of activities
issuance request review form (CDM-ISSR-FORM)
(Version 03.0)

Project title of the project activity or programme of activities (PoA) for which issuance is requestedAWMS Methane Recovery Project BR06-S-27, Goias, Brazil (1162)
DOE that requested for issuance and date of requestDNV (14 Jul 10)
Please indicate, in accordance with paragraphs 65 of the CDM modalities and procedures, for which reason(s) you request review
Incompetence
Please indicate reasons for the request for review
As per the monitoring report (p 18), Landtec meter serial no. GM11592 was used to take methane concentration reading on 20 April 2009 at site no. 21902. While the monitoring report (p 14) indicates that the Landtec meter GM11592 was first calibrated on 24 April 2009, the monitoring plan requires that prior to the use of Landtec meter, it should be calibrated. Therefore the DOE is required to further clarify whether GM11592 had a valid calibration when reading was taken at site 21902 on 20 April 2009. If the meter did not have a valid calibration then adjustment should be applied to the emission reductions as per Guidelines of EB52 Annex 60.
Date 12 Mar 11