Project: 1032 Shandong Shanxian 1*25MW Biomass Power Plant Project - Crediting Period Renewal Request
[]
Project 1032: Shandong Shanxian 1*25MW Biomass Power Plant Project

- project design document (1272 KB)

PDD appendices
Appendix 1 - ER_Shanxian biomass_Renewal_ref.1032 (119 KB)

- crediting period renewal form (122 KB)
Methodologies Used ACM0018 ver. 3 - Electricity generation from biomass residues in power-only plants
VVS Version VVS 9.0
Standardized baselines used N/A
Amount of Reductions 80,251 metric tonnes CO2 equivalent per annum
Validation Opinion Validation opinion (911 KB)
Renewal Date 23 Jun 17 (Renewable)   (view history)   completeness check: complete info & rep check: concluded
Crediting Period (requested for renewal) 17 Jun 14 - 16 Jun 21

Other crediting period(s): 17 Jun 07 - 16 Jun 14
Requests for Issuance
and related documentation