Project: 1005 Gansu Diebu Niaojiaga 12.9 MW Hydropower Station Project - Issuance Request
Project 1005: Gansu Diebu Niaojiaga 12.9 MW Hydropower Station Project
 
ISSUANCE STATUS Issued (on 03 May 13)   completeness check: complete | info & rep check: concluded
Monitoring period 29 Apr 12 - 31 Dec 12
Monitoring report Monitoring report (228 KB)
 
Request for issuance Signed form (88 KB)
Amount of CERs CERs issued up to 31 December 2012: 49,244
Serial Range: Block start: CN-5-808536026-1-1-0-1005     Block end: CN-5-808585269-1-1-0-1005
Verification and certification reports VVS/VVM version: VVS 3.0
Certification report (724 KB)
Verification report (724 KB)
Additional documents 1005 6 Monitoring Report (227 KB)
1005 6 CER Calculation (66 KB)