Issuance Request for Review Form


CDM project activity/programme of activities
issuance request review form (CDM-ISSR-FORM)
(Version 03.0)

Project title of the project activity or programme of activities (PoA) for which issuance is requestedBundled Wind power project in Tamilnadu, India co-ordinated by the TamilNadu Spinning Mills Association (TASMA) (0991)
DOE that requested for issuance and date of requestDNV (13 Nov 08)
Please indicate, in accordance with paragraphs 65 of the CDM modalities and procedures, for which reason(s) you request review
Incompetence
Please indicate reasons for the request for review
1. Further clarification is required on how the DOE verified that the approach of applying the electricity generation from the two WEGs connected to HTSC No.740 as electricity supply to the grid, is in accordance with the revised monitoring plan which requires that the net electricity supplied to the grid (export minus import) to be measured by meters at substation and certified by TNEB statement.
Other Issue:
2. Further information is required on the electricity generation data measured by the power meters installed at substations in accordance with the revised monitoring plan.
Date 11 Dec 08