CDM project activity/programme of activities issuance request review form (CDM-ISSR-FORM) (Version 03.0) |
---|
Project title of the project activity or programme of activities (PoA) for which issuance is requested | Rudong County Wind Farm Project – China (0491) |
---|---|
DOE that requested for issuance and date of request | DNV (26 Jun 08) |
Please indicate, in accordance with paragraphs 65 of the CDM modalities and procedures, for which reason(s) you request review | |
Incompetence | |
Please indicate reasons for the request for review | |
The DOE is requested to clarify how it has verified that: 1. The baseline emission factor was calculated yearly as mentioned in section D.2.2 of the PDD. 2. The requirement of the monitoring plan for conducting the calibration of electricity meters every six months was met. |
|
Date | 25 Jul 08 |