Issuance Request for Review Form


CDM project activity/programme of activities
issuance request review form (CDM-ISSR-FORM)
(Version 03.0)

Project title of the project activity or programme of activities (PoA) for which issuance is requestedARAPUtanga Centrais ELétricas S. A. - ARAPUCEL - Small Hydroelectric Power Plants Project (0530)
DOE that requested for issuance and date of requestTÜV NORD (03 Sep 09)
Please indicate, in accordance with paragraphs 65 of the CDM modalities and procedures, for which reason(s) you request review
Incompetence
Please indicate reasons for the request for review
It is noted that the capacity of the Alto Juaru hydropower plant has increased from 20 MW, stated in the
PDD, to 21.96 MW. The DOE is requested to clarify why it did not notify and request for approval of the
changes in the PDD (as per Annex 66 to EB 48) prior to requesting the issuance of CERs.
Date 04 Dec 09