Issuance Request for Review Form


CDM project activity/programme of activities
issuance request review form (CDM-ISSR-FORM)
(Version 03.0)

Project title of the project activity or programme of activities (PoA) for which issuance is requestedCatalytic N2O destruction project in the tail gas of the Nitric Acid Plant of Abu Qir Fertilizer Co. (0490)
DOE that requested for issuance and date of requestDNV (14 Nov 08)
Please indicate, in accordance with paragraphs 65 of the CDM modalities and procedures, for which reason(s) you request review
Incompetence
Please indicate reasons for the request for review
1. The DOE is requested to clarify that on 10th April, and 15th –20th April 2008 when outlet analyser was out of operation and sent for calibration/maintenance activity respectively, how the PP demonstrated that the destruction facility was operational at normal efficiency.
2.The PP is requested to clarify what back up plans it has for such situation when the measuring equipments are out of service, to ensure that the quality of monitoring parameter is not affected.
Date 15 Dec 08