Issuance Request for Review Form
CDM project activity/programme of activities issuance request review form (CDM-ISSR-FORM) (Version 03.0) |
---|
Project title of the project activity or programme of activities (PoA) for which issuance is requested | AWMS GHG Mitigation Project BR05-B-08, Paraná and Rio Grande do Sul, Brazil (0466) |
---|---|
DOE that requested for issuance and date of request | DNV (05 Dec 07) |
Please indicate, in accordance with paragraphs 65 of the CDM modalities and procedures, for which reason(s) you request review | |
Incompetence | |
Please indicate reasons for the request for review | |
The verification report (p.5-6) states that EB47 accepted a deviation regarding the calculation of 'percentage of biogas that is methane'. However, the DOE has not requested the said deviation for the project activity. Clarification is required. | |
Date | 31 Dec 09 |