18:56 22 Feb 25
Issuance Request for Review Form
CDM project activity/programme of activities issuance request review form (CDM-ISSR-FORM) (Version 03.0) |
---|
Project title of the project activity or programme of activities (PoA) for which issuance is requested | AWMS GHG Mitigation Project BR05-B-13, Goiás and Minas Gerais, Brazil (0419) |
---|---|
DOE that requested for issuance and date of request | DNV (21 Aug 09) |
Please indicate, in accordance with paragraphs 65 of the CDM modalities and procedures, for which reason(s) you request review | |
Incompetence | |
Please indicate reasons for the request for review | |
1. The PP/DOE shall clarify the list of electricity consumption equipments of all the sites, since the verification report (p.9) states that only “For a sample of sites, the list of equipment considered in the calculation was cross-checked with the equipment installed at the site…”. Other Issues 2. The DOE states that the portable gas analyser is being sent annually for manufacturer calibration (on page 8 of verification report) while the PP indicates that the frequency of manufacturer recalibation is every 6 months (on page13 of monitoring report). Clarification is required. |
|
Date | 23 Nov 09 |