Project title of the project activity or programme of activities (PoA) for which issuance is requestedAlta Mogiana Bagasse Cogeneration Project (AMBCP) (0181)
DOE that requested for issuance and date of requestSGS (10 Dec 08)
Please indicate, in accordance with paragraphs 65 of the CDM modalities and procedures, for which reason(s) you request review
Incompetence
Please indicate reasons for the request for review
The DOE is requested to clarify the reason for increase in emission reduction from 26,214 as estimated in the PDD to 39,676 during the monitoring period, in particular, the changes in the gross electricity generation from the project, electricity supplied for consumption in the mill and net electricity supplied to the grid.
Date 23 Jan 09