| Project | 9065: Yunnan Hongtutian 18MW Hydroelectric Project |
|---|---|
| ISSUANCE STATUS | Issued (on 16 Jun 17) completeness check: complete | info & rep check: concluded |
| Monitoring period | 01 Jan 13 - 30 Sep 16 |
| Monitoring report |
Monitoring report (547 KB)
|
| Request for issuance |
Signed form (458 KB)
|
| Amount of CERs |
CERs issued from 01 Jan 2013 until 31 December 2020:
98,328
Serial Range:
Block start: CN-5-1046555488-2-2-0-9065
Block end: CN-5-1046653815-2-2-0-9065
|
| Verification and certification reports |
VVS/VVM version:
VVS 9.0
Certification report (702 KB)
Verification report (702 KB)
|
| Additional documents |
MR (691 KB)
ER sheet (23 KB)
|

Monitoring report
ER sheet