17:51 23 Jul 25
Project
6628 :
Jiangsu Guoxin Dongling 48MW Windfarm Phase II Project
Project title |
Jiangsu Guoxin Dongling 48MW Windfarm Phase II Project
- ![]() PDD appendices ![]() ![]() ![]() - ![]() |
---|---|
SDC description report | Not Available. Please refer to our Further Information on SD-Tool |
Host Parties |
China
, involved indirectly
![]() ![]() Authorized Participants: Jiangsu Guoxin Dongling Wind Power Development Co., Ltd. |
Other Parties Involved |
France
, involved indirectly
![]() ![]() Authorized Participants: EDF Trading Limited |
Sectoral scopes | 1 : Energy industries (renewable - / non-renewable sources) |
Activity Scale | LARGE |
Methodologies Used |
ACM0002 ver. 12 -
Consolidated baseline methodology for grid-connected electricity generation from renewable sources
|
Standardized baselines used | N/A |
Amount of Reductions | 82,261 metric tonnes CO2 equivalent per annum |
Fee level | USD 14952.2 |
Validation Report |
VVS/VVM version:
VVM 1.2
![]() Link to information uploaded for public availability |
Modalities of Communication |
MoC Annex 1 Modalities of Communication valid as of 10/10/2012 |
Registration Date | 13 Jul 12 (Date of registration action 08 Oct 12) (view history) completeness check: complete info & rep check: concluded |
Crediting Period |
16 Jul 12 - 15 Jul 19
(Renewable)
Subsequent crediting period(s): 16 Jul 19 - 15 Jul 26 |
Requests for Issuance
and related documentation |
Monitoring report: ![]() Issuance request state: Issued CERs requested up to 31 December 2012: 33241 CERs requested from 01 Jan 2013 until 31 December 2020: 99879 Serial Range: Block start: CN-5-904973122-1-1-0-6628 Block end: CN-5-905006362-1-1-0-6628 Serial Range: Block start: CN-5-905006363-2-2-0-6628 Block end: CN-5-905106241-2-2-0-6628 [Full view and history] |
Offset now: visit the United Nations Carbon Offset Platform