Reference number of the proposed CDM project activity/programme of activities (PoA) submitted for registration | 5100 |
---|---|
Title of the proposed CDM project activity/PoA submitted for registration | Boxing Biogas Recovery and Utilization Project in Shandong Province |
Please indicate, in accordance with paragraphs 37 and 40 of the CDM modalities and procedures, which validation requirement(s) may require review. A list of requirements is provided below. Please provide reasons in support of the request for review. Including any supporting documentation. | |
The following are requirements derived from paragraph 37 of the CDM modalities and procedures: | |
![]() ![]() ![]() ![]() ![]() ![]() ![]() |
|
The following are requirements derived from paragraph 40 of the CDM modalities and procedures: | |
![]() ![]() ![]() ![]() ![]() ![]() |
|
![]() |
|
Additional information | |
1) The DOE should further explain how it has validated the input values to the investment analysis, in line with the VVM v. 1.2, para. 111(a), in particular: (a) the investment cost - (ii) how it is broken down into the different equipment to be installed as indicated in the PDD, and based on its sectoral expertise, that the costs assumed for individual equipment are reasonable; and (ii) whether the upgrading facility is dedicated to the project activity and that the fixed asset investment costs are properly allocated to the output of the project activity; and (b) the O&M cost, in particular, the appropriateness of the "raw biogas purchase cost" (or "material fees" as it is referred to in the spreadsheet) which accounts for 50% of the total, considering that the biogas from the starch plant was vented in the baseline. Please refer to VVM v. 1.2, para. 111(a): "To verify the accuracy of financial calculations carried out for any investment analysis, the DOE shall: (a) Conduct a thorough assessment of all parameters and assumptions used in calculating the relevant financial indicator, and determine the accuracy and suitability of these parameters using the available evidence and expertise in relevant accounting practices.". 2) The DOE shall: (a) confirm whether all the upgraded biogas is sold as bottled biogas in line with the statement in the PDD on p. 21 that as the natural gas distribution grid has not been constructed yet, the upgraded biogas is all bottled for sale; and (b) further explain how it has considered that the project activity complies with the requirements of para. 6 of AMS III-H v. 15, para. 6, given that the end-users of bottled gas are outside the project boundary. Please refer to AMS III-H v. 15, para. 6: "For project activities covered under paragraph 3 (b), if bottles with upgraded biogas are sold outside the project boundary, end-use of the biogas shall be ensured via a contract between the bottled biogas vendor and the end-user. No emission reductions may be claimed from the displacement of fuels from the end use of bottled biogas in such situations.". 3) The DOE is requested to explain how it has considered that the methodology is correctly applied to determine the emission reductions due to the displacement of fossil fuel based natural gas given that according to the PDD, all of the upgraded biogas is bottled for sale and that the end-users are outside the project boundary. Please refer to AMS III.H, v16, Annex 1, para. 1: “In case of project activities covered under paragraph 3 (b) and (c), if the project activity involves bottling of biogas the project boundary includes the upgrade and compression installations, the dedicated piped network/natural gas distribution grid for distribution of biogas from the wastewater treatment plant to the end user sites and all the facilities and devices connected directly to it.”. 4) The DOE should explain how it has considered that the monitoring of "the method to avoid captured biogas venting into the air when the upgrading facility is closed" is in line with para 16 (f) of Annex I of the methodology which requires the project participants to ensure that the captured biogas is flared at the site of its capture using an (emergency) flare and to establish appropriate monitoring procedures to monitor this emergency flare. Please refer to AMS III.H, v16, Annex 1, para. 16 (f): "During the periods when the biogas upgrading facility is closed due to scheduled maintenance or repair of equipment or during exigencies, project participants should ensure that the captured biogas is flared at the site of its capture using an (emergency) flare. Appropriate monitoring procedures should be established to monitor this emergency flare.". |
|
Date | 19 Nov 11 |