00:08 24 Nov 26
Project:
3767 Xinjiang Uygur Autonomous Region Kashgar Tarim River Xiabandi Hydropower Station
- Issuance Request
| Project | 3767: Xinjiang Uygur Autonomous Region Kashgar Tarim River Xiabandi Hydropower Station |
|---|---|
| ISSUANCE STATUS | Issued (on 14 Sep 11) completeness check: complete | info & rep check: concluded |
| Monitoring period | 15 Nov 10 - 27 Apr 11 |
| Monitoring report |
Monitoring report (172 KB)
|
| Request for issuance |
Signed form (125 KB)
|
| Amount of CERs |
CERs issued up to 31 December 2012:
122,238
Serial Range:
Block start: CN-5-419334807-1-1-0-3767
Block end: CN-5-419457044-1-1-0-3767
|
| Verification and certification reports |
Certification report (43 KB)
Verification report (438 KB)
|
| Additional documents |
CER calculation sheet -3767 (45 KB)
Monitoring report Ver 02-3767 (172 KB)
|

Monitoring report
CER calculation sheet -3767
Offset now: visit the United Nations Carbon Offset Platform
Connect with us: