Reference number of the proposed CDM project activity/programme of activities (PoA) submitted for registration | 3390 |
---|---|
Title of the proposed CDM project activity/PoA submitted for registration | Yunnan Baoshan Songshanhekou Hydropower Station |
Please indicate, in accordance with paragraphs 37 and 40 of the CDM modalities and procedures, which validation requirement(s) may require review. A list of requirements is provided below. Please provide reasons in support of the request for review. Including any supporting documentation. | |
The following are requirements derived from paragraph 37 of the CDM modalities and procedures: | |
![]() ![]() ![]() ![]() ![]() ![]() ![]() |
|
The following are requirements derived from paragraph 40 of the CDM modalities and procedures: | |
![]() ![]() ![]() ![]() ![]() ![]() |
|
![]() |
|
Additional information | |
1. The DOE shall further validate the appropriateness of applying the coefficient of effective electricity for a 168 MW project as the DOE confirmed its appropriateness based on document Economic Evaluation Code for Small Hydropower Project (SL16-95) which appears to be applicable for small scale hydro projects only. 2. The DOE is requested to further substantiate the common practice analysis, as the essential distinctions between the project activity and the other similar hydro projects identified have not been sufficiently substantiated in accordance with VVM version 01 paragraph 118. In particular, the DOE shall justify the appropriateness of applying the operational hours and unit of investment cost as the means of comparison. |
|
Date | 22 Nov 10 |