1304 Henan Zhengzhou Grid Connected Natural Gas Combined Cycle Power Plant
- Issuance Request
Project | 1304: Henan Zhengzhou Grid Connected Natural Gas Combined Cycle Power Plant |
---|---|
ISSUANCE STATUS | Issued (on 30 Aug 10) |
Monitoring period | 01 Jan 09 - 30 Nov 09 |
Monitoring report | Monitoring report (252 KB) |
Request for issuance | Signed form (50 KB) |
Amount of CERs |
CERs issued up to 31 December 2012:
376,935
Serial Range:
Block start: CN-5-213852926-1-1-0-1304
Block end: CN-5-214229860-1-1-0-1304
|
Verification and certification reports |
Certification report (24 KB)
Verification report (191 KB) |
Additional documents |
ER spreadsheet (137 KB)
Revised monitoring report (337 KB) |