19:50 12 Jul 25
Project:
3524 Caojie Hydropower Project on Jiangling River in Chongqing City
- Issuance Request
Project | 3524: Caojie Hydropower Project on Jiangling River in Chongqing City |
---|---|
ISSUANCE STATUS | Issued (on 30 Nov 12) completeness check: complete | info & rep check: concluded |
Monitoring period | 01 Feb 12 - 30 Jun 12 |
Monitoring report |
![]() |
Request for issuance |
![]() |
Amount of CERs |
CERs issued up to 31 December 2012:
363,118
Serial Range:
Block start: CN-5-662632495-1-1-0-3524
Block end: CN-5-662995612-1-1-0-3524
|
Verification and certification reports |
VVS/VVM version:
VVM 1.2
![]() ![]() |
Additional documents |
![]() ![]() |