Issuance Request for Review Form
CDM project activity/programme of activities issuance request review form (CDM-ISSR-FORM) (Version 03.0) |
---|
Project title of the project activity or programme of activities (PoA) for which issuance is requested | Jiangxi Luohongkou 8.25MW Hydropower Project, China (2432) |
---|---|
DOE that requested for issuance and date of request | DTSUS (20 May 10) |
Please indicate, in accordance with paragraphs 65 of the CDM modalities and procedures, for which reason(s) you request review | |
Incompetence | |
Please indicate reasons for the request for review | |
The PDD indicates a turbine type JP502-LH-190 (rated flowing of 22.81m3/s) to be installed in the project activity, however the DOE verified that a turbine type ZDJP502-LH-190 (rated flowing 22.92m3/s) has been installed instead. The DOE should clarify how it verified the project implementation in relation to the registered PDD and explain why a request for changes in PDD has not been submitted prior to the first request for issuance as per EB48 Annex 66. | |
Date | 23 Sep 10 |