Project: 3684 Inner Mongolia Jingneng Chayouzhong Wind Farm Phase II Project - Issuance Request
Project 3684: Inner Mongolia Jingneng Chayouzhong Wind Farm Phase II Project
 
ISSUANCE STATUS Issued (on 25 Oct 13)   completeness check: complete | info & rep check: concluded
Monitoring period 03 Nov 10 - 31 Aug 11
Monitoring report Monitoring report (224 KB)
 
Request for issuance Signed form (482 KB)
Amount of CERs CERs issued up to 31 December 2012: 95,088
Serial Range: Block start: CN-5-856312190-1-1-0-3684     Block end: CN-5-856407277-1-1-0-3684
Verification and certification reports VVS/VVM version: VVS 3.0
Certification report (62 KB)
Verification report (666 KB)
Additional documents ER_Calculation_Spreadsheet_Jingneng_Chayouzhong_VR8261_Ref_3684-1 (69 KB)
zhongme_Monitoring_Report_Jingneng_Chayouzhong_VR8261_Ref_3684-1 (331 KB)