Project:
3462 Bangkok Kamphaeng Saen East: Landfill Gas to Electricity Project
- Issuance Request
Project | 3462: Bangkok Kamphaeng Saen East: Landfill Gas to Electricity Project |
---|---|
ISSUANCE STATUS | Issued (on 17 Oct 19) completeness check | info & rep check: concluded |
Monitoring period | 21 Jan 18 - 31 Oct 18 |
Monitoring report |
![]() |
Request for issuance |
![]() |
Amount of CERs |
CERs issued from 01 Jan 2013 until 31 December 2020:
85,950
Serial Range:
Block start: TH-5-14344063-2-2-0-3462
Block end: TH-5-14430012-2-2-0-3462
|
Verification and certification reports |
VVS/VVM version:
VVS-PA 2.0
![]() ![]() |
Additional documents |
![]() ![]() |
Previous submissions
Submission date | Outcome |
---|---|
01 Feb 19 | CC complete | I&R incomplete |