17:31 17 Jul 24
Registration Request for Review Form
CDM project activity/programme of activities registration request review form (CDM-REGR-FORM) (Version 03.0) |
---|
Reference number of the proposed CDM project activity/programme of activities (PoA) submitted for registration | 2860 |
---|---|
Title of the proposed CDM project activity/PoA submitted for registration | 3.00 MW bundled Wind Power Project by Shree Jai Ambe Associates at Brahmanvel, Dist. Dhule (Maharashtra), India |
Please indicate, in accordance with paragraphs 37 and 40 of the CDM modalities and procedures, which validation requirement(s) may require review. A list of requirements is provided below. Please provide reasons in support of the request for review. Including any supporting documentation. | |
The following are requirements derived from paragraph 37 of the CDM modalities and procedures: | |
![]() ![]() ![]() ![]() ![]() ![]() ![]() |
|
The following are requirements derived from paragraph 40 of the CDM modalities and procedures: | |
![]() ![]() ![]() ![]() ![]() ![]() |
|
![]() |
|
Additional information | |
1. The DOE should further explain how the suitability of the calculated benchmark has been validated, considering the type of IRR calculation conducted for each of the four windmills. 2. The DOE should explain how it has validated the suitability of the PLF and the escalation rate of 7.5% in the O&M cost in the investment analysis, in line with the VVM para. 109 (a) and (b). 3. The DOE is requested to clarify how it has validated the appropriateness of the monitoring plan, in particular: (a) why the measurements from the common feeder are not directly used to calculate the net electricity generated by the project activity, and (b) why the imported electricity is calculated based on the exported electricity. |
|
Date | 16 Nov 09 |
Offset now: visit the United Nations Carbon Offset Platform
Connect with us: