Reference number of the proposed CDM project activity/programme of activities (PoA) submitted for registration | 2760 |
---|---|
Title of the proposed CDM project activity/PoA submitted for registration | “100 MW Malana – II, Hydro – Electric Power Project (Malana – II HEP)” at Kullu district of Himachal Pradesh State, India, by M/s Everest Power Private Limited |
Please indicate, in accordance with paragraphs 37 and 40 of the CDM modalities and procedures, which validation requirement(s) may require review. A list of requirements is provided below. Please provide reasons in support of the request for review. Including any supporting documentation. | |
The following are requirements derived from paragraph 37 of the CDM modalities and procedures: | |
![]() ![]() ![]() ![]() ![]() ![]() ![]() |
|
The following are requirements derived from paragraph 40 of the CDM modalities and procedures: | |
![]() ![]() ![]() ![]() ![]() ![]() |
|
![]() |
|
Additional information | |
1. The DOE should further validate that the project start date is in line with the CDM "Glossary of Terms". 2. The PP/DOE should explain the difference between the IRR indicated in the PDD and spreadsheet submitted for registration. If a new spreadsheet is provided, the PP/DOE should clearly explain all the differences between the new spreadsheet and the one submitted for registration. The spreadsheet submitted contains circular references. 3. The DOE should further validate: (a) that the input values sourced from the DPR were applicable at the time of investment decision; (b) the change in the auxiliary consumption form 0.3% to 0.7% referred in CAR9; (c) the O&M cost's 4% annual escalation and; (d) the primary generation/total energy generated, transformation and transmission losses, in line with the VVM para. 109. 4. The DOE should further validate: (a) why ±10% variations in the total investment and electricity generation are unlikely to occur and; (b) the appropriateness of excluding the tariff in the sensitivity analysis, in line with EB 51, Annex 58, paragraphs 17 and 18. 5. The PP and DOE should further explain how the net electricity and the total electricity produced by the project activity (TEGy) will be calculated/measured. 6. PDD's Sections E.2 and E.3 make reference to attached documents which have not been uploaded. 7. The DOE should clarify how it has closed the Stakeholder comment part 03, 25/01/08, in line with the VVM para. 38 and 41. |
|
Date | 06 Feb 10 |