01:13 24 Nov 24
Issuance Request for Review Form
CDM project activity/programme of activities issuance request review form (CDM-ISSR-FORM) (Version 03.0) |
---|
Project title of the project activity or programme of activities (PoA) for which issuance is requested | Bionersis project on La Duquesa landfill, Dominican Republic (2595) |
---|---|
DOE that requested for issuance and date of request | GLC (24 Aug 11) |
Please indicate, in accordance with paragraphs 65 of the CDM modalities and procedures, for which reason(s) you request review | |
Incompetence | |
Please indicate reasons for the request for review | |
1) The monitoring plan of the registered PDD does not include the monitoring of the parameter FCdiesel (Quantity of diesel fired in the captive power plant during the monitoring period), however, its consumption has been reported in the Monitoring Report. Besides, the monitoring of FC has not been conducted in accordance with the methodology and applied methodological tool, which requires the use of weight or volume meters, and its reporting in Mass or (normalized) volume unit per year (in m³, ton or l). Instead, the volume is reported in gallons. Please refer to VVM Paragraph 204.. | |
Date | 19 Nov 11 |
Offset now: visit the United Nations Carbon Offset Platform
Connect with us: