13:11 16 Jun 25
Registration Request for Review Form
CDM project activity/programme of activities registration request review form (CDM-REGR-FORM) (Version 03.0) |
---|
Reference number of the proposed CDM project activity/programme of activities (PoA) submitted for registration | 2375 |
---|---|
Title of the proposed CDM project activity/PoA submitted for registration | CERTEL – Cooperativa Regional de Eletrificação Teutônia Ltda - Small Hydropower Plants |
Please indicate, in accordance with paragraphs 37 and 40 of the CDM modalities and procedures, which validation requirement(s) may require review. A list of requirements is provided below. Please provide reasons in support of the request for review. Including any supporting documentation. | |
The following are requirements derived from paragraph 37 of the CDM modalities and procedures: | |
![]() ![]() ![]() ![]() ![]() ![]() ![]() |
|
The following are requirements derived from paragraph 40 of the CDM modalities and procedures: | |
![]() ![]() ![]() ![]() ![]() ![]() |
|
![]() |
|
Additional information | |
1. The DOE is requested to clarify further how it has validated that the plant load factor (PLF) for the project. In doing so, DOE shall validate and cross check, based on reliable and credible evidence, the appropriateness of application of sensitivity analysis on the PLF and the O&M costs. 2. Further clarification is requested from the DOE on how they have validated that the project is not a common practice. In doing so, the credible evidence and sources of such information shall be provided. |
|
Date | 01 Sep 09 |