Project:
2265 42.5 MW Wind Power Project by VRL Logistics Ltd in Karnataka State (India)
- Issuance Request
Project | 2265: 42.5 MW Wind Power Project by VRL Logistics Ltd in Karnataka State (India) |
---|---|
ISSUANCE STATUS | Issued (on 22 Dec 22) completeness check: complete | info & rep check: concluded |
Monitoring period | 01 Feb 18 - 21 Mar 19 |
Monitoring report |
![]() |
Request for issuance |
![]() |
Amount of CERs |
CERs issued from 01 Jan 2013 until 31 December 2020:
63,787
Serial Range:
Block start: IN-5-311891006-2-2-0-2265
Block end: IN-5-311954792-2-2-0-2265
|
Verification and certification reports |
VVS/VVM version:
VVS-PA 3.0
![]() ![]() |
Additional documents |
![]() ![]() |