13:49 21 Dec 24
Registration Request for Review Form
CDM project activity/programme of activities registration request review form (CDM-REGR-FORM) (Version 03.0) |
---|
Reference number of the proposed CDM project activity/programme of activities (PoA) submitted for registration | 2042 |
---|---|
Title of the proposed CDM project activity/PoA submitted for registration | The Rotem Amfert Negev (RAN) Natural Gas Fuel Switch Project |
Please indicate, in accordance with paragraphs 37 and 40 of the CDM modalities and procedures, which validation requirement(s) may require review. A list of requirements is provided below. Please provide reasons in support of the request for review. Including any supporting documentation. | |
The following are requirements derived from paragraph 37 of the CDM modalities and procedures: | |
The participation requirements as set out in paragraph 28 to 30 of the CDM modalities and procedures are satisfied; Comments by local stakeholders have been invited, a summary of the comments received has been provided, and a report to the designated operational entity (DOE) on how due account was taken of any comments has been received; Project Participants have submitted to the DOE documentation on the analysis of the environmental impacts of the project activity, including transboundary impacts and, if those impacts are considered significant by the project participants or the host Party, have undertaken an environmental impact assessment in accordance with procedures as required by the host Party; The project activity is expected to result in a reduction in anthropogenic emissions by sources of greenhouse gases that are additional to any that would occur in the absence of the proposed project activity, in accordance with paragraphs 43 to 52 of the CDM modalities and procedures; The baseline and monitoring methodologies comply with requirements pertaining to methodologies previously approved by the Executive Board; Provisions for monitoring, verification and reporting are in accordance with decision 17/CP.7, the CDM modalities and procedures and relevant decisions of the COP/MOP; The project activity conforms to all other requirements for CDM project activities in decision 17/CP.7, the CDM modalities and procedures and relevant decisions by the COP/MOP and the Executive Board. |
|
The following are requirements derived from paragraph 40 of the CDM modalities and procedures: | |
The DOE shall, prior to the submission of the validation report to the Executive Board, have received from the project participants written approval of voluntary participation from the designated national authority of each Party involved, including confirmation by the host Party that the project activity assists it in achieving sustainable development; In accordance with provisions on confidentiality contained in paragraph 27(h) of the CDM modalities and procedures, the DOE shall make publicly available the project design document; The DOE shall receive, within 30 days, comments on the validation requirements from Parties, stakeholders and UNFCCC accredited non-governmental organizations and make them publicly available; After the deadline for receipt of comments, the DOE shall make a determination as to whether, on the basis of the information provided and taking into account the comments received, the project activity should be validated; The DOE shall inform project participants of its determination on the validation of the project activity. Notification to the project participants will include confirmation of validation and the date of submission of the validation report to the Executive Board; The DOE shall submit to the Executive Board, if it determines the proposed project activity to be valid, a request for registration in the form of a validation report including of the project design document, the written approval of the host Party and an explanation of how it has taken due account of comments received. |
|
There are only minor issues which should be addressed by the DOE/project participants prior to the registration of the project. | |
Additional information | |
1. The PP/DOE is requested to provide the detailed description of the entire plant in addition to that of the project and supported by the detailed and complete process-flow-diagram, explaining clearly the inputs and outputs. In doing this, the PP/DOE are also requested to provide clarifications regarding: (a) how many dryers are to be retrofitted and how many burners (include types) are to be installed; (b) what are the inputs (fuels, raw materials, etc) and outputs (products, etc) from the dryer; (c) if NG has been used in the plant prior to the project, either as a fuel or a process raw material. 2. The PP/DOE are also requested to describe how the ‘output from the dryer’ has been defined in the project context and the procedure and method to measure the ‘output from the dryer’ and confirm that the requirements of paragraph 5 of AMS-III.B. version 12 are complied with. 3. The DOE is requested to clarify how they have validated that the price differential between the HFO and the NG has been considered in the selection of the baseline scenario and that this price differential is not the main driver to implement the project activity. 4. The DOE is requested to clarify how they have validated that the quantity of HFO actually consumed in the dryer can be accurately measured/ estimated from the receipts of the HFO delivered to the site and not by actual monitoring, considering that HFO has also been used in process other than the dryer. In doing so, the DOE is requested to confirm that the monitoring procedure of HFO, diesel, NG and the output from the dryer will not lead to any uncertainty in the measurement and is in line with the requirements of paragraph 9 of AMS-III.B. version 12. |
|
Date | 15 Jan 09 |
Offset now: visit the United Nations Carbon Offset Platform
Connect with us: