Project: 1897 Sichuan Pingshan Pingbian&Guanyintuo Hydropower Station - Issuance Request
Project 1897: Sichuan Pingshan Pingbian&Guanyintuo Hydropower Station
 
ISSUANCE STATUS Issued (on 19 Apr 13)   completeness check: complete | info & rep check: concluded
Monitoring period 26 Jul 12 - 25 Dec 12
Monitoring report Monitoring report (184 KB)
 
Request for issuance Signed form (80 KB)
Amount of CERs CERs issued up to 31 December 2012: 71,538
Serial Range: Block start: CN-5-802272881-1-1-0-1897     Block end: CN-5-802344418-1-1-0-1897
Verification and certification reports VVS/VVM version: VVS 3.0
Certification report (289 KB)
Verification report (289 KB)
Additional documents 1897-20130130-MR (185 KB)
1897-20130130-CER SHEET (25 KB)