Project: 1897 Sichuan Pingshan Pingbian&Guanyintuo Hydropower Station - Issuance Request
Project 1897: Sichuan Pingshan Pingbian&Guanyintuo Hydropower Station
 
ISSUANCE STATUS Issued (on 27 Dec 12)   completeness check: complete | info & rep check: concluded
Monitoring period 26 Sep 11 - 25 Jul 12
Monitoring report Monitoring report (73 KB)
 
Request for issuance Signed form (90 KB)
Amount of CERs CERs issued up to 31 December 2012: 110,479
Serial Range: Block start: CN-5-694345912-1-1-0-1897     Block end: CN-5-694456390-1-1-0-1897
Verification and certification reports VVS/VVM version: VVS 2.0
Certification report (208 KB)
Verification report (208 KB)
Additional documents 1897- MR-2012 09 28 (77 KB)
1897- 3_Pingbian&Guanyintuo ER sheet_for submission_20120926- 2012 09 28 (33 KB)