CDM project activity/programme of activities issuance request review form (CDM-ISSR-FORM) (Version 03.0) |
---|
Project title of the project activity or programme of activities (PoA) for which issuance is requested | Fuel Switching Project of the Aqaba Thermal Power Station (ATPS) (1758) |
---|---|
DOE that requested for issuance and date of request | DNV (08 Jul 10) |
Please indicate, in accordance with paragraphs 65 of the CDM modalities and procedures, for which reason(s) you request review | |
Incompetence | |
Please indicate reasons for the request for review | |
The PP/DOE shall justify and, if appropriate, correct the calculations of leakage emissions for upstream CH4 associated with baseline fuel HFO. It is noted that the PP calculated it using formula electricity generation (MWh) / power plant efficiency (%) x HFO NCV (TJ/t) x upstream CH4 emission factor (tCH4/TJ), whereas it should be calculated as (electricity generation (MWh) / power plant efficiency (%))x upstream CH4 emission factor (tCH4/TJ) x conversion factor (TJ/MWh), considering that the formula used resulted in overestimation of leakage associated with baseline fuel thus resulted in underestimation of overall leakages applied for emission reduction calculations. | |
Date | 06 Nov 10 |