Issuance Request for Review Form
CDM project activity/programme of activities issuance request review form (CDM-ISSR-FORM) (Version 03.0) |
---|
Project title of the project activity or programme of activities (PoA) for which issuance is requested | Beijing Taiyanggong CCGT Trigeneration Project (1320) |
---|---|
DOE that requested for issuance and date of request | DNV (30 Oct 08) |
Please indicate, in accordance with paragraphs 65 of the CDM modalities and procedures, for which reason(s) you request review | |
Incompetence | |
Please indicate reasons for the request for review | |
The DOE is requested to clarify how it verified the measurement of net electricity supplied to the grid using meters M4 and M5, which were planned to be installed on the two 220kV transmission lines to Sun He power station, that were not commissioned during the verification period. | |
Date | 13 Nov 08 |