17:40 22 Apr 25
Project:
1253 Baragran Hydro Electric Project, 3.0 MW (being expanded to 4.9 MW)
- Issuance Request
Project | 1253: Baragran Hydro Electric Project, 3.0 MW (being expanded to 4.9 MW) |
---|---|
ISSUANCE STATUS | Issued (on 26 Jul 13) completeness check: complete | info & rep check: concluded |
Monitoring period | 01 Jan 12 - 31 Dec 12 |
Monitoring report |
![]() |
Request for issuance |
![]() |
Amount of CERs |
CERs issued up to 31 December 2012:
23,460
Serial Range:
Block start: IN-5-182441045-1-1-0-1253
Block end: IN-5-182464504-1-1-0-1253
|
Verification and certification reports |
VVS/VVM version:
VVS 3.0
![]() ![]() |
Additional documents |
![]() ![]() |
Offset now: visit the United Nations Carbon Offset Platform
Connect with us: