Project:
1253 Baragran Hydro Electric Project, 3.0 MW (being expanded to 4.9 MW)
- Issuance Request
| Project | 1253: Baragran Hydro Electric Project, 3.0 MW (being expanded to 4.9 MW) |
|---|---|
| ISSUANCE STATUS | Issued (on 03 Dec 20) completeness check: complete | info & rep check: concluded |
| Monitoring period | 01 Apr 18 - 31 Dec 19 |
| Monitoring report |
Monitoring report (629 KB)
|
| Request for issuance |
Signed form (36 KB)
|
| Amount of CERs |
CERs issued from 01 Jan 2013 until 31 December 2020:
45,506
Serial Range:
Block start: IN-5-261076658-2-2-0-1253
Block end: IN-5-261122163-2-2-0-1253
|
| Verification and certification reports |
VVS/VVM version:
VVS-PA 2.0
Certification report (288 KB)
Verification report (288 KB)
|
| Additional documents |
Untitled (uploaded 04 Aug 20 19:45:54) (445 KB)
Untitled (uploaded 04 Aug 20 19:47:51) (30 KB)
|

Monitoring report
Untitled (uploaded 04 Aug 20 19:47:51)